Financial Scheme

1. 2% Down Payment Home Loan Scheme

Home Loan (Construction Linked)
Milestone % Due Customer Contribution Bank Contribution
Down Payment 2% 2% 0%
Within 30 days 28% 0% 28%
Plinth 15% 0% 15%
5th Slab 5% 0% 5%
10th Slab 5% 0% 5%
15th Slab 5% 0% 5%
20th Slab 5% 0% 5%
22nd Slab 5% 0% 5%
On completion of the walls, internal plaster, floorings door and windows 5% 5% 0%
Promoter on completion of the sanitary fittings, staircases, lift, lobbies upto the floor level of the said flat 5% 5% 0%
on completion of the external plumbing and external plaster, elevation, terraces with waterproofing of the building or wing in which the said flat is located 5% 5% 0%
on completion of the lifts, water pumps, electrical fittings, electro, mechanical and environment requirements, entrance lobby/s, plinth protection paving of areas appertain. 11% 4% 7%
At the time of Offer of the possession of the said flat to the Purchaser on or before receipt of occupancy certificate or completion certificate. 4% 0% 4%

* Stamp Duty, Registration charges and Legal Charges to be paid along with Down Payment
**GSTto be paid as demanded by Developer

2. Self Funding Financing

Self Funding (Construction Linked)
Milestone % Due
Down Payment 10%
Within 30 days 20%
Plinth 15%
5th Slab 5%
10th Slab 5%
15th Slab 5%
20th Slab 5%
22nd Slab 5%
On completion of the walls, internal plaster, floorings door and windows 5%
Promoter on completion of the sanitary fittings, staircases, lift, lobbies upto the floor level of the said flat 5%
on completion of the external plumbing and external plaster, elevation, terraces with waterproofing of the building or wing in which the said flat is located 5%
on completion of the lifts, water pumps, electrical fittings, electro, mechanical and environment requirements, entrance lobby/s, plinth protection paving of areas appertain. 10%
At the time of Offer of the possession of the said flat to the Purchaser on or before receipt of occupancy certificate or completion certificate. 5%

* Stamp Duty, Registration charges and Legal Charges to be paid along with Down Payment
**GST to be paid as demanded by Developer